Five base options proposed for America’s Cup

Five base options proposed for America’s Cup

0 개 2,233 노영례

6db36834b74c0f6d11b142cfc5f00f09_1510551110_7431.jpg
 

Auckland Council’s Governing Body will next week be asked to approve a team base location for hosting the 36th America’s Cup in 2021.

On 13 November, councillors were presented with five infrastructure options for hosting the event, which will add between $550 million and $1 billion* in direct benefits to the New Zealand economy.

Decision required by 23 November

Auckland Council Chief Executive Stephen Town says a decision on a location is required at the Governing Body meeting on 23 November to allow for resource consent to be lodged in January.

“The main America’s Cup races are likely to be held from January to March 2021, so to meet the event’s timeframes and the anticipated arrival of syndicates, construction needs to be substantially complete by mid to late 2019,” he says.

Council, government, Emirates Team New Zealand work on requirements

Since Emirates Team New Zealand’s (ETNZ) victory in the America’s Cup in late June, the council has been working closely with the government and ETNZ on the infrastructure requirements to deliver the 2021 event.

Panuku Development Auckland, the city’s regeneration agency, has led this work and its Design and Place Director Rod Marler says technical experts have undertaken a robust evaluation of a longlist of possible locations across the Auckland region.

“The locations have been evaluated based on three key criteria: ability to deliver in the timeframe (consented and constructed by late 2019), ability to meet the requirements of the teams and event (such as security and an event village), and the extent to which any investment delivers a legacy for Auckland and New Zealand,” says Marler.

The five short-listed options are

  • Halsey Wharf extension
  • Captain Cook West
  • Captain Cook East
  • a dispersed option across Halsey Wharf and Westhaven Marina
  • a dispersed option across Halsey Wharf, Hobson Wharf and Wynyard Point East.

See below for full details of the five options. 

Costs range from $140m-$190m

Stephen Town says the indicative costs for the five options range from $140 million to $190 million.

“This funding will be included in the council’s Long-term Plan, on the basis that a funding package will need to be negotiated, sharing costs between the council, the government and private sector investors,” he says.

“We understand that the government will consider its involvement next month, with decisions in early 2018.”

Town added that the Governing Body will also consider the consent process that will be required to meet the event deadline.

“While this is an exciting opportunity for Auckland both around the actual event in 2021 and for the legacy that any event infrastructure can deliver for the city, we also understand the need for a great environmental outcome,” he says.

Previous events brought more than $1b in benefits

Steve Armitage, General Manager Destination at Auckland Tourism, Events and Economic Development (ATEED), says hosting two previous America’s Cup regattas delivered more than $1 billion in total benefits for New Zealand – mainly in tourism and the marine industry.

“The regattas of 2000 and 2003 were momentous for our region in numerous ways, and the benefits went well beyond our lion’s share of the national economic injection,” he says.

“The events showcased Auckland to the world, and preparing for the regattas was the catalyst for waterfront transformation – a legacy Aucklanders still benefit from today.”

“It’s estimated that extra economic activity generated by the 2003 regatta alone sustained more than 8100 full-time equivalent jobs, which was nearly 2 per cent of Auckland’s employment at that time,” says Armitage.

ETNZ has stated a strong preference to hold the event in Auckland, but reserves the right to hold the event in Italy if suitable infrastructure is not available. The deadline for a final announcement on the location is 31 August 2018.

Full details of base location options

Halsey Wharf extension

Aerial view of port area of Auckland showing possible locations for America
  • Wharf structure/location consistent with the intent of Waterfront Plan 2012
  • Meets event requirements, and provides a legacy for the marine and events sectors with new sheltered water space.

Captain Cook West

Aerial view of port area of Auckland showing possible locations for America
  • Uses existing wharf infrastructure plus an extension
  • Meets event requirements and close to amenities such as Shed 10 and The Cloud.

Captain Cook East

Aerial view of port area of Auckland showing possible locations for America
  • Uses existing wharf infrastructure plus an extension
  • Meets event requirements and close to amenities but does turn its back on Queens Wharf.

Dispersed - Halsey Wharf and Westhaven Marina

Aerial view of port area of Auckland showing possible locations for America
  • Westhaven development and Halsey Wharf extension consistent with the intent of Waterfront Plan 2012
  • Delivers new sheltered water space to provide for the growth of the marine and event sectors.

Dispersed - Halsey Wharf, Hobson Wharf and Wynyard Point East

Dispersed - Halsey Wharf,  Hobson Wharf and  Wynyard Point East
  • Central village location, close to existing amenities
  • Wharf structure in this location consistent with the intent of the Waterfront Plan 2012. Delivers the new opportunity of sheltered water space to provide for the growth of the marine and events sector.

*Note to editors:

The Ministry of Business, Innovation and Employment commissioned a study by Market Economics on the potential economic impact of Auckland hosting the 36th America’s Cup. The study stated that hosting the 2021 America’s Cup will add between $555 and $977 million to the New Zealand economy. That figure is simply the direct benefits of hosting the event. It does not consider the benefits of any new infrastructure, or ongoing benefits to the marine industry.

출처 : Auckland Council News

House prices flatten in April

댓글 0 | 조회 430 | 5일전
Home value growth in Aote… 더보기

Government cuts put 130 jobs on the line at K…

댓글 0 | 조회 327 | 5일전
The Government's cuts to … 더보기

Borrowers bet on rate cuts by locking in shor…

댓글 0 | 조회 563 | 2024.04.18
Kiwi borrowers are bettin… 더보기

Business as usual for cash rate and housing m…

댓글 0 | 조회 268 | 2024.04.10
Commentary by CoreLogic N… 더보기

Residential recovery sluggish in first quarte…

댓글 0 | 조회 266 | 2024.04.09
Residential property valu… 더보기

Soft start for NZ housing market in March qua…

댓글 0 | 조회 629 | 2024.04.04
CoreLogic's House Price I… 더보기

The new-build premium could be about to shrin…

댓글 0 | 조회 331 | 2024.03.30
We estimate that new-buil… 더보기

STARS OF TV AND SYMPHONY ALIGN FOR CHILDREN’S…

댓글 0 | 조회 369 | 2024.03.19
Howls of What's the time … 더보기

Housing recovery spreads to nearly 60% of NZ …

댓글 0 | 조회 408 | 2024.03.14
Property values rose in a… 더보기

Annual growth back in black despite flat Febr…

댓글 0 | 조회 453 | 2024.03.12
Property values are sligh… 더보기

No OCR change... for now

댓글 0 | 조회 726 | 2024.02.28
Today's decision by the R… 더보기

Construction cost growth continuing to cool

댓글 0 | 조회 339 | 2024.02.28
The average cost of build… 더보기

Property sale volumes remain erratic

댓글 0 | 조회 621 | 2024.02.20
High mortgage rates conti… 더보기

Home values continue to strengthen, slowly bu…

댓글 0 | 조회 728 | 2024.02.13
The housing market's slow… 더보기

Profitable resales rise for the first time in…

댓글 0 | 조회 629 | 2024.02.08
93.3% of property resales… 더보기

MetService launches push notifications for Ne…

댓글 0 | 조회 566 | 2024.01.25
From today 25 January, Ki… 더보기

Property market signs off 2023 on a strong no…

댓글 0 | 조회 521 | 2024.01.17
The CoreLogic House Price… 더보기

Heat comes out of the construction sector as …

댓글 0 | 조회 434 | 2024.01.11
As pressures on residenti… 더보기

What the shortened Brightline test means for …

댓글 0 | 조회 530 | 2023.12.21
Following the Government’… 더보기

Housing upturn broadens, but underwhelming 20…

댓글 0 | 조회 734 | 2023.12.20
TheCoreLogic NZ December … 더보기

Slow recovery to be continued in 2024

댓글 0 | 조회 567 | 2023.12.19
The housing market contin… 더보기

New Zealanders' Standard of Living in Freefal…

댓글 0 | 조회 965 | 2023.12.14
Responding to today’s rel… 더보기

A turning point for the NZ housing market

댓글 0 | 조회 687 | 2023.12.13
A 'year of two halves' ap… 더보기

10 things to know about mortgage debt right n…

댓글 0 | 조회 1,211 | 2023.12.06
The housing loan market h… 더보기

Home values rise 0.7% in November

댓글 0 | 조회 1,166 | 2023.12.01
Hot on the heels of Octob… 더보기