Micro Tunnel Boring Machine begins tunnelling and inserts first pipe for groundbreaking Central Interceptor project

Micro Tunnel Boring Machine begins tunnelling and inserts first pipe f…

0 개 963 노영례

d60ce9a1edde06f10ebb9be06915f8c3_1623445220_991.png
 

A micro–Tunnel Boring Machine (mTBM) called ‘Domenica’ has started digging and laying the first pipe for Watercare’s Central Interceptor wastewater tunnel project.

The 12-metre long mTBM laid the first three metre section of the 2.1-metre diameter pipe at the May Rd, Mount Roskill site on 4 June. Another 328 pipe sections will follow over the next four months to create the first of two link sewers, which will branch off the main Central Interceptor Tunnel.

The mTBM will travel up to 18 metres per day.  Digging will take place 24 hours a day, six days per week to complete the first drive.

Watercare chief executive officer, Jon Lamonte says laying the first pipe underground is a major milestone: “It’s a great day for everyone on the Central Interceptor team. Congratulations to everyone involved in reaching this important milestone.”

An underground operator runs the mTBM, which uses a pipe-jacking method of construction. The first link sewer to be completed will travel from May Rd to Miranda Reserve in Avondale. The second will start near the Mt Albert War Memorial and travel 1.5 kilometres to the Ōrākei sewer main.

TBMs are traditionally given female names and Domenica is named after Italian relatives of Ghella, one of the partners in the Ghella Abergeldie Joint Venture, which is delivering the project. She was manufactured in Germany and refurbished in Thailand.





Once completed in 2025, the Central Interceptor will run almost 15 kilometres underground from Grey Lynn to the Māngere Wastewater Treatment Plant. The $1.2 billion project will drastically reduce wet-weather overflows in Central Auckland waterways, which occur when stormwater floods the system during heavy rain.

The main TBM, Hiwa-i-te-rangi will begin its journey digging the major tunnel from Māngere in July. She is currently lying in sections close to the shaft and is being prepared for launch. Large cranes are carefully lifting 17 gantries into place around the shaft edge, ready for the lowering operation in coming weeks.

The Central Interceptor is the largest wastewater project in New Zealand history.

Once completed, the Central Interceptor will be the longest bored tunnel in New Zealand. Providing both storage and conveyance, it will hold the equivalent of 80 Olympic-sized swimming pools and act as a buffer for the wastewater treatment plant in times of high flow.

10 things to know about the mortgage market r…

댓글 0 | 조회 290 | 7일전
Given the scrapping of fi… 더보기

Reserve Bank sticks firmly to the script

댓글 0 | 조회 280 | 2024.05.23
Today's decision by the R… 더보기

Movers' could be a group to watch

댓글 0 | 조회 345 | 2024.05.22
The surge in available li… 더보기

Broadband prices in 223 countries revealed. N…

댓글 0 | 조회 1,050 | 2024.05.20
Auckland, New Zealand - N… 더보기

Property resale profits dip as market shifts …

댓글 0 | 조회 540 | 2024.05.16
The resale performance of… 더보기

NZ cleantech delegation heading to South Kore…

댓글 0 | 조회 880 | 2024.05.15
Eleven business leaders f… 더보기

Winter is coming − what's in store for the ho…

댓글 0 | 조회 407 | 2024.05.14
It's shaping up to be ano… 더보기

Weaker property prices mean more 'bang for bu…

댓글 0 | 조회 1,061 | 2024.05.08
The country's first home … 더보기

House prices flatten in April

댓글 0 | 조회 588 | 2024.05.02
Home value growth in Aote… 더보기

Government cuts put 130 jobs on the line at K…

댓글 0 | 조회 378 | 2024.05.02
The Government's cuts to … 더보기

Borrowers bet on rate cuts by locking in shor…

댓글 0 | 조회 635 | 2024.04.18
Kiwi borrowers are bettin… 더보기

Business as usual for cash rate and housing m…

댓글 0 | 조회 307 | 2024.04.10
Commentary by CoreLogic N… 더보기

Residential recovery sluggish in first quarte…

댓글 0 | 조회 334 | 2024.04.09
Residential property valu… 더보기

Soft start for NZ housing market in March qua…

댓글 0 | 조회 691 | 2024.04.04
CoreLogic's House Price I… 더보기

The new-build premium could be about to shrin…

댓글 0 | 조회 364 | 2024.03.30
We estimate that new-buil… 더보기

STARS OF TV AND SYMPHONY ALIGN FOR CHILDREN’S…

댓글 0 | 조회 404 | 2024.03.19
Howls of What's the time … 더보기

Housing recovery spreads to nearly 60% of NZ …

댓글 0 | 조회 456 | 2024.03.14
Property values rose in a… 더보기

Annual growth back in black despite flat Febr…

댓글 0 | 조회 481 | 2024.03.12
Property values are sligh… 더보기

No OCR change... for now

댓글 0 | 조회 759 | 2024.02.28
Today's decision by the R… 더보기

Construction cost growth continuing to cool

댓글 0 | 조회 378 | 2024.02.28
The average cost of build… 더보기

Property sale volumes remain erratic

댓글 0 | 조회 669 | 2024.02.20
High mortgage rates conti… 더보기

Home values continue to strengthen, slowly bu…

댓글 0 | 조회 772 | 2024.02.13
The housing market's slow… 더보기

Profitable resales rise for the first time in…

댓글 0 | 조회 660 | 2024.02.08
93.3% of property resales… 더보기

MetService launches push notifications for Ne…

댓글 0 | 조회 609 | 2024.01.25
From today 25 January, Ki… 더보기

Property market signs off 2023 on a strong no…

댓글 0 | 조회 570 | 2024.01.17
The CoreLogic House Price… 더보기